CompTIA Network+ Question C-61

A network engineer is designing a new IDF in an old building. The engineer determines the equipment will fit in a two-post rack, and there is power available for this equipment. Which of the following would be the FIRST issue to remediate?

A. Air flow and cooling
B. UPS capability
C. Circuit labeling
D. Power redundancy

Correct Answer: A